A warehouse floor can look ready for coating and still have two problems you cannot see from a photograph: weak concrete beneath the surface and moisture within the slab. And a crack that looks small may still be moving. Before choosing a resin finish, agree on what has to be repaired, how the prepared surface will be accepted, and who can release each area back to traffic.

This guide covers new and existing concrete in warehouses and workshops. It is a planning and inspection checklist, not a method statement for any one epoxy, polyurethane or polyurethane mortar system. The project specification and the current technical data sheets (TDS) and safety data sheets (SDS) govern the products and conditions used on site. See FeRFA’s resin flooring specification and application guide for the relationship between design, preparation, application and testing.

Inspection gates, not a coating recipe
  1. Inspect the slabMap conditions and unresolved risks
  2. Accept preparationCheck repairs, profile and conditions
  3. Check each coatRecord materials, timing and defects
  4. Release by useConfirm traffic and cleaning readiness

Pause at an unresolved gate. These checkpoints do not approve a product or site.

Inspect the slab before specifying the finish

Walk the floor with the installer and mark conditions on a plan. Separate normal storage bays from forklift turning areas, loading doors, machine bases, wet zones and drains. Record the intended traffic, likely oils or chemicals and cleaning routine for each zone. In a renovated building, include past uses, previous repairs, the age and condition of any existing coating, and any recurring problems. Make clear in the quote which areas are known to be sound and which still need investigation.

CheckWhat to recordHold work if…
Slab and ground supportFor slabs on ground, ask for available slab, subbase and vapour retarder records. Map settlement, changes in level across cracks and joints, and recurring damage.There is suspected settlement, slab movement or a load-capacity question. Refer it to the project engineer before treating it as a surface repair.
Concrete and old coatingMark dusting, laitance (a weak surface layer), hollow or loose areas, peeling coatings and existing repairs. Agree how to verify substrate strength or adhesion where required.Concrete is weak or an old coating’s bond and compatibility are unknown. Don’t bury an unverified layer under the new finish.
MoistureIdentify leaks, damp areas and evidence of previous blistering. Agree the test method, locations and acceptance limit with the system supplier. Log the date and conditions.Moisture results are outside the system limit, the source of water is unresolved, or a screening reading is being used in place of the specified test.
Levels and detailsMark high spots, depressions, changes at doors, drainage falls, cracks, joints and potholes. Ask which levels and falls must be preserved.Deep depressions, exposed reinforcement, unstable edges or unplanned changes in drainage remain outside the agreed work scope.

Soil support is not a coating issue. A resin finish does not stabilise the ground beneath a slab, restore structural capacity or correct settlement. The ACI guide to slabs on ground explains why soil support, loading and slab design need separate engineering review. For an existing floor, include removal and preparation in the renovation quotation scope.

Check concrete moisture before approving the slab

Agree on the test method, locations and acceptance limit for the selected flooring system before testing. The plastic-sheet check can flag possible moisture; in-situ relative humidity (RH) measures conditions inside the slab. Neither a clear sheet nor a low surface-meter reading is a reason to skip a specified test.

Plastic-sheet check: a qualitative indication, not a release test

The ASTM D4263 plastic-sheet check looks for visible signs of moisture. As described in AMPP’s concrete moisture guide, tape all four edges of a clear polyethylene sheet about 18 × 18 in (460 × 460 mm) to the concrete and leave it for at least 16 hours. Follow the edition specified for the job, keep the sheet out of direct heat or sunlight, and record the location, times and site conditions.

If you find droplets under the sheet or darkening of the covered concrete, hold coating and investigate. If you see neither, that tells you only what was visible at that spot under those conditions. The check gives no numerical reading and cannot clear the slab for coating.

Clear plastic taped to concrete at left; a gloved hand lifts the sheet at right.
Left: seal all four edges of the clear sheet to the concrete. Right: after the specified wait, lift the sheet and look for droplets on its underside or darker concrete beneath it. This is a qualitative check, not a release test.

In-situ RH testing: measure inside the slab

When the job calls for ASTM F2170, use in-slab probes under the specified edition. Record the location, depth, conditions, timing and RH reading, then compare the results with the limit for the selected system. An electronic surface meter can help map suspect areas, but it does not measure in-slab RH or replace the specified test.

Surface moisture meter on the left; a probe sleeve and cap in the concrete on the right.
Left: a surface meter used to locate suspect areas. Right: a sleeve for an in-slab RH probe. Neither panel shows a test reading. See a surface-meter example (Tramex CME5) and an in-slab probe demonstration (Wagner Rapid RH).

What to record before coating: Test method, result and units, test date, bay or grid location, slab and room conditions, and any wet or below-grade areas. Compare the reading to the limit for that method in the specified system. Do not compare in-slab RH directly with a mass-percent result. A water-based primer is not automatically a moisture barrier. If the readings do not support release, establish the source of moisture and agree on the next test or treatment before priming.

Choose mechanical preparation by the profile it leaves

Prepared concrete surface showing its roughness
Concrete texture examples, from finer to heavier. They do not establish CSP numbers or a fixed machine-to-profile mapping. Compare the specified profile with official ICRI physical reference chips; appearance alone is not acceptance.

The preparation specification should name the surface condition to achieve, not just the machine to hire. Start by dealing with contaminants such as oil and grease and determining whether existing coatings must be removed. Then remove weak surface material and create the profile required by the proposed resin system. Where the specification uses numbers, Concrete Surface Profile (CSP) denotes the resulting surface texture, not the equipment setting. The ICRI reference range is CSP 1–10. Compare representative prepared areas on site with physical ICRI replica chips visually and by feel as a screening check. Do not assign a CSP grade from a photograph or infer it from the machine used. The required roughness criteria, tolerances and acceptance method remain those in the specification; tactile comparison is not a substitute for required measurement. See the ICRI field reference discussion and DeFelsko’s visual and tactile CSP comparison guidance. Check the edges, corners, repairs and thresholds as well as the middle of each bay. See the International Concrete Repair Institute’s surface preparation guidance.

  • Diamond grinding can remove high spots or coatings and prepare smaller or restricted areas. Check the result: a smooth, polished track is not the same as the specified bonding profile.
  • Shot blasting can profile large, accessible areas. Check overlaps and separately detail strips that the large machine cannot reach.
  • Scarifying or milling can remove thicker build-up or deteriorated material. Check the remaining concrete and whether further preparation is needed; grooves left by the machine are not automatically an acceptable finish for the next coat.

The same machine can leave different profiles on different slabs. After preparation, keep traffic off the area. Use suitable filtered vacuum or wet-cleaning methods under the site exposure-control plan. Do not blow dust into the work area or use dry sweeping. If wet preparation is used, remove slurry and reverify the substrate condition required by the coating system before application. Use FeRFA’s surface preparation guide to compare preparation methods. Mechanical preparation can generate respirable crystalline silica. Have a qualified contractor choose and verify task-specific controls under the applicable local rules; OSHA’s walk-behind grinder fact sheet gives a US example. Control dust exposure during the work, not only during final cleaning.

Repair cracks, potholes and joints as different defects

Handheld groove cutter with an extraction hose
Handheld groove cutter connected to an extraction hose. Specify the tool, PPE, groove profile and cutting location for the project.

Cracks: Determine whether the crack is dormant, moving, or still unclassified before choosing a repair. If an assessed dormant crack is suitable for a bonded repair, use the specified compatible detail. If it is moving, reopening or displaced, have it assessed rather than filling it rigidly and coating over it. A finish is not a structural crack repair.

Potholes and spalls: Remove loose and deteriorated material to sound concrete, and reassess the depth and limits once the damaged area is open. Use a repair material rated for the actual depth, service conditions and adjacent layers. Follow that material’s instructions for preparation, placement, cure and readiness to overcoat. Check repair levels against the surrounding floor or drainage fall before coating. Deep damage, exposed reinforcement and widespread deterioration call for engineering review. The US Bureau of Reclamation’s concrete repair guide explains why identifying the cause and removing unsound concrete come before material choice.

Joints: Mark and identify existing isolation, expansion, control and construction joints on the plan. Keep required movement joints functional through the floor build-up; don’t turn them into rigid patch lines. If forklift wheels are breaking a saw-cut joint edge, assess both the edge damage and the joint’s intended movement before choosing a filler, sealant or edge detail. Record the edge repair and the movement-joint detail separately so the installer knows which areas must remain flexible.

Anchorage grooves: Cut these where the selected PU-cement system explicitly requires them, for example at specified free edges, drains, terminations or day joints. Confirm the actual locations and geometry in that system’s detail before marking or cutting. Heavy loading, a thick coating or a polyurethane label alone does not establish this requirement. Keep movement joints separate and functional.

Check dew point and early-cure conditions

A slab that meets its internal moisture limit can still develop surface condensation. Before mixing or applying any coating, record air temperature, relative humidity, substrate temperature and calculated dew point using the agreed instruments and method. Where the selected system specifies a 3 °C (about 5 °F) dew-point margin, keep the substrate at least that far above the dew point. Recheck conditions during application and early cure as directed by the system’s technical data sheet.

Cold conditions and condensation may impair adhesion or appearance. Some epoxy formulations can develop amine blush during cure, especially in cool, humid conditions. If a film appears on the surface, check its cause and follow the system supplier’s cleaning and recoating instructions before applying the next coat.

Apply the specified layers and check each before covering it

Treat primer, intermediate build and finish as separate items on the method statement. Some systems omit a layer or use a different sequence. Confirm the specified build-up, compatibility and nominal thickness for each layer before work starts.

  1. Prime or seal as specified. Check that the repair areas and main slab are ready, then apply the approved primer or sealer. Inspect the result for missed patches, pooling or defects that the specified next coat cannot cover. If a test area reacts differently over a repair or an old coating, resolve it before coating the rest of the bay.
  2. Build or level the intermediate layer where specified. Check repair levels, falls and thickness transitions before adding a build coat. Agree where filling or levelling is separate work. Inspect the intermediate layer before covering it, including edges and repaired zones.
  3. Apply the wearing finish. Use the tool and method named in the current system instructions. Keep the finish continuous to the detailed edges and preserve required joints. Record finished thickness by the agreed method where the specification requires it. The floor coating thickness guide shows how to distinguish cured film, total system build and tool size.
  4. Protect and cure by zone. Set access barriers before starting. Keep the zone out of use until the person named in the specification verifies the required checks and releases it for the planned activity. Record any different release conditions for foot traffic, vehicles and cleaning.

Check the TDS and SDS buyer checklist for document identity, component labels and revision. If the floor will be regularly washed, persistently damp or submerged, review the water exposure and drainage checks before selecting any finish.

Agree on three sign-offs before the work starts

MilestoneWhat gets checkedRecord before proceeding
Before primer or first coatSurface is sound, clean and at the specified profile; repair and joint treatments are accepted; moisture and environmental checks meet the project requirements.Zone plan, photos of the trial area and details, measurement results and sign-off.
Between coatsConfirm the actual materials and batches, required mix basis, site temperature and humidity, condensation risk, and current recoat window. Inspect for contamination, missed spots or other defects before covering a layer.Per-zone application times and conditions; any defect or missed window and the corrective action agreed with the system supplier.
Before reopeningVerify the finish and joints against the specification, including any required tests. Check actual cure conditions and release separately for foot traffic, forklifts, cleaning or chemical exposure as applicable.A zone-by-zone release record, remaining restrictions and maintenance instructions. A floor that feels dry is not evidence that it is ready for full use.

Plan phasing around these sign-offs. If a night shift prepares the surface before the morning crew coats it, agree who protects it from dust and traffic and who rechecks conditions before application. Keep barriers and signs in place until the relevant release, rather than promising an opening time on the assumption that curing will match ideal conditions. Use the current SDS and the site’s safety plan for handling, ventilation, protection and isolation during work.

Two warehouse and workshop examples

Illustrative examples, not Jinlang project case studies.

Active warehouse with worn forklift aisles. A smooth-looking storage bay and a loading aisle with chipped control-joint edges should not receive the same repair allowance without inspection. Ask for separate prices for qualified surface preparation, joint-edge repairs and the coating work. Agree on a trial bay that includes a joint and a turning area. Before reopening, confirm readiness for forklifts, not just people.

Maintenance workshop with oil staining and shallow potholes. Mark stained areas separately from clean concrete. Ask the contractor how they will check whether oil remains after cleaning and preparation, and how they will assess the depth and edges of each pothole. Quote local patching or broader levelling separately from the resin finish. A self-levelling finish is not a substitute for deep repairs, nor should it be used to flatten out a required fall to a drain.

What to send with a flooring enquiry

Send a marked-up plan and approximate area, photos of the slab and damaged details, slab and moisture records if available, traffic and cleaning conditions, and the periods when work and reopening are possible. Ask the supplier to identify the proposed layers, the acceptance checks and what is excluded, so you can compare quotations on the same scope.

View industrial floor coatings or prepare a floor project enquiry.

The contact page prepares an enquiry for you to send. Attach photographs and reports in your email client.

For post-handover care, plan routine cleaning, spill response and local wear checks.